Change Request [CR-number]
Project: [name] · Statement of work: [SOW number and date] · Date raised: [date]
Requested by: [name, company] · Prepared by: [name, your company]
1. Requested change
[Describe the change in one or two sentences, e.g. “Add a members-only area with login, profile page and downloadable resources.”]
2. Reason for the change
[Why the client wants it, e.g. “Sales team needs a place to share gated content with prospects.”]
3. Impact
| Scope | [What is added, removed or replaced] |
| Effort | [Estimated hours or days] |
| Cost | [Amount and currency], excluding [VAT / GST / sales tax] |
| Timeline | [e.g. launch moves from 14 Oct to 28 Oct] |
| Other effects | [e.g. extra hosting cost, new third-party licence, more testing] |
4. Options
- A. Approve the change as described, at the cost and timeline above.
- B. Swap it for [an in-scope item of similar size], with no change to cost or timeline.
- C. Defer it to a later phase and keep the current plan.
5. Decision
Option chosen: [A / B / C] · Payment: [added to next invoice / invoiced on approval]
Approved for Client: ____________________ Name: __________ Date: __________
Approved for Provider: ____________________ Name: __________ Date: __________
Work on this change starts only after both approvals.